[Date Prev][Date Next][Thread Prev][Thread Next] - [Date Index][Thread Index][Author Index]
STS-112 STATUS REPORT 26 SEPT 2002
- Subject: [sarex] STS-112 STATUS REPORT 26 SEPT 2002
- From: azrowe@xxxxxxxx
- Date: Thu, 26 Sep 2002 20:19:46 -0400
Submitted by Arthur - N1ORC
KENNEDY SPACE CENTER
SHUTTLE & PAYLOAD PROCESSING STATUS REPORT
Thursday, September 26, 2002 (2:00 p.m.)
Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC
Home Page for the latest schedule of future Shuttle missions. For the
latest Shuttle status visit
http://www-pao.ksc.nasa.gov/kscpao/status/stsstat/current.htm
MISSION STS-112 -- 15TH ISS FLIGHT (9A) – S1 Truss
VEHICLE: Atlantis/OV-104
TARGET LAUNCH DATE: Oct. 2, 2002 NET
TARGET LAUNCH PERIOD: 2 – 6 p.m. EDT
TARGET LANDING DATE: Oct. 13, 2002
MISSION DURATION: 11 days
CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees
Shuttle Processing Note: Final preparations for Atlantis’ lift-off to the
International Space Station next week continue in work. Launch countdown
preparations continue, aft closeouts continue with doors scheduled for
installation today. The Extravehicular Mobility Units also have been
installed and checked out. Mission managers continue to monitor several
tropical storms though none are expected in the KSC vicinity in the near
term and no work is being held up as we proceed on schedule for launch.
________________________________________________________________
GET INTERNET ACCESS FROM JUNO!
Juno offers FREE or PREMIUM Internet access for less!
Join Juno today! For your FREE software, visit:
http://dl.www.juno.com/get/web/.
----
Via the sarex mailing list at AMSAT.ORG courtesy of AMSAT-NA.
To unsubscribe, send "unsubscribe sarex" to Majordomo@amsat.org
AMSAT Home